Forthcoming Roadworks in the Ealing Area
Closures and diversions which may cause problems

Lane Closures on North Circular Near Chiswick Roundabout to Resume
Work on improving Gunnersbury Avenue safety to last through to Summer
B455 South Ealing Road, Ealing |
28 March — 04 April |
Delays likely Traffic control (multi-way signals) |
Works description: excavation works - telecoms mast maintenance - hiab in carriageway, pedestrian walkway to be installed in carriageway, three way traffic lights to be used |
Responsibility for works: O2 (UK) Limited |
Current status: Planned work about to start |
Works reference: MG08043832/CLS/SJTM |
Murray Road, Ealing |
25 March — 02 April |
Delays likely Road closure |
Works description: Consequential damage in carriageway |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU026002141FGSF--001001 |
|
A4000,A40 Western Avenue, Acton |
03 April — 04 April |
Delays likely Lane closure |
Works description: BLOCK CLOSURE WB# TESTING LIGHTS & BOLLARDS, BULK CLEAN & CHANGE, SWEEPING, GULLY & BEANY BLOCK CLEANING, BARRIER WORKS, GRASS CUTTING, SIGN CLEANING, DEBRIS PATROLS |
Responsibility for works: Transport for London |
Current status: Planned work about to start |
Works reference: YG431368267 |
|
A4020 Broadway, West Ealing |
03 April — 09 April |
Delays likely Lane closure |
Works description: New Water Supply HH Plots 1-6, 6x25mm MDPE mtrd 6P Supply works infoo tway and in Carriageway. Our intention is to complete the PermanentReinstatement in the same phase |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU307000808200620135-001 |
|
A40 Western Avenue, Perivale |
02 April — 03 April |
Delays likely Lane closure |
Works description: Routine maintenance of LEZ system |
Responsibility for works: Transport for London |
Current status: Planned work about to start |
Works reference: YG53115000945 |
|
A40 Western Avenue, Perivale |
02 April — 03 April |
Delays likely Lane closure |
Works description: Routine maintenance of LEZ system |
Responsibility for works: Transport for London |
Current status: Planned work about to start |
Works reference: YG53115000946 |
|
B4491 Popes Lane, Ealing |
18 March — 24 May |
Delays likely Traffic control (multi-way signals) |
Works description: EXCAVATE TRENCH INSTALL CABLE CARRY OUT JOINTING BACKFILL AND REINSTATE |
Responsibility for works: Scottish and Southern Power Distribution |
Current status: Planned work about to start |
Works reference: LP705S30001052 |
|
A406 Gunnersbury Avenue (north Circular Road) |
15 March — 29 March |
Delays likely Lane closure |
Works description: Works to reinstate the eastern footway of the A406 Gunnersbury Avenue over the Power Road Bridge. Works will require a Lane 1 SB for a safety zone. Works coordinated with the Gunnersbury Safety Scheme Phase 2. TM 24/7 |
Responsibility for works: Transport for London |
Current status: Planned work about to start |
Works reference: YG400402049 |
A4000, A40 Western Avenue, Acton |
27 February — 23 September |
Delays likely Road closure |
Works description: Cycle Super Highway 10 - reconstruction and installation of new cycle way - section 58 required |
Responsibility for works: Transport for London |
Current status: Advanced planning |
Works reference: YG432342348 |
|
Westway, Hammersmith and Fulham |
27 February — 23 September |
Delays likely Road closure |
Works description: Cycle Super Highway 10 - reconstruction and installation of new cycle way - section 58 required |
Responsibility for works: Transport for London |
Current status: Advanced planning |
Works reference: YG432342350 |
|
April 2, 2019
|