A406,A4005 Hanger Lane, Ealing

17 August — 19 August

Delays likely Traffic control (two-way signals)

Works location: A406,A4005

Works description: Tfl Maintenance Work - Re-Cut Loops And Terminate Into Existing Cabinet

Responsibility for works: Transport For London

Current status: Planned work about to start

A4020,B455 The Broadway, Ealing

14 August — 16 August

Delays likely Lane closure

Works location: A4020,B455

Works description: Virgin Media - New Connection, Connect From Existing F/W Duct And Excavate Back To The Property And Install A F/W Tee

Responsibility for works: Virgin Media

Current status: Planned work about to start

A4020 Uxbridge Road, Ealing

14 August — 16 August

Delays likely Traffic control (give & take)

Works location: A4020

Works description: Gully Renewal Works

Responsibility for works: Ealing London Borough Council

Current status: Work in progress

A4020 Uxbridge Road, Ealing

14 August — 25 August

Delays likely Lane closure

Works location: A4020

Works description: Install 17m Of 1 Way Poly Duct In Carriageway,Install 68m Of 1 Way Poly Duct In Footway

Responsibility for works: BT

Current status: Planned work about to start

A4020 Uxbridge Road, West Ealing

14 August — 25 August

Delays likely Lane closure

Works location: A4020

Works description: Install 31m Of 1 Way Poly Duct In Footway,Install 3m Of 1 Way Poly Duct In Carriageway

Responsibility for works: BT

Current status: Planned work about to start

B455 Castlebar Road, Ealing

14 August — 22 August

Delays likely Traffic control (two-way signals)

Works location: B455

Works description: Imgc 180094-130014148 Lay A New 63mm Main To Site To Feed 4 Newservices, Connection To Existing Main In Carriageway Opposite.

Responsibility for works: Cadent

Current status: Planned work about to start

Uxbridge Road, Southall

14 August — 17 August

Delays likely Lane closure

Works location: -

Works description: -

Responsibility for works: O2 (UK) Limited

Current status: Planned work about to start

Western Avenue, Greenford
26 July - 06 May 2018
Delays likely Road closure
Works location: -
Works description: -
Responsibility for works: Transport For London
Current status: Planned work about to start

Gunnersbury Avenue (North Circular Road)

07 June — 16 November 2018

Delays likely Lane closure

Works location: -

Works description: -

Responsibility for works: Transport For London

Current status: Planned work about to start

 