Meet the Team on September 27
After months of preparation, September  saw a major milestone in Mogden’s £140m extension. 
            
            We have now switched on around half  of the new works, including the new inlet area and primary tanks - where  solid and heavy particles are removed. 
            
            This step has allowed us to start taking  the existing uncovered primary tanks on the west side of the works out  of service so that they can be upgraded, and then covered to control odour. 
            
            We are now gearing up to gradually switch  on the remainder of the new works by the end of March 2013. At this point  the site's treatment capacity will have been boosted by 50 per cent so  it can cope better following heavy rain. 
            
            As we get closer to reducing the embankment  to its final height by the end of the year, there will be an increase in  activity in this area, particularly at the northern end as we remove our  construction offices. You may notice some vibration as a result. 
            
            We are committed to minimising this  as best as we can but we are sorry for any disruption you may experience. 
            
            By the end of this month we will be  returning to our normal working hours, between 8am and 6pm for the main  activities. This follows weeks of working on the embankment until 7pm to  recover time lost as a result of this year's unusually wet weather. 
            
            Thank you for bearing with us. 
            
            Come and meet the team 
            On Thursday September 27, from 5pm to  6.30pm, we will be holding an informal drop-in session where you will be  able to discuss the improvement work at Mogden with members of the project  team. 
            
            This will be held at Twickenham Stadium.  On arrival please report to reception at Rugby House Door A, situated in  the South Stand. Free car parking is available in the main car park and  refreshments will be provided. 
            
            We will continue to update you on our  progress, but if you have any questions please call 0845 641 0030 and quote  ‘Mogden’. Our lines are always open. 
                  
Thames Water
       
September 25, 2012