With less than a year to go before we increase  Mogden’s treatment capacity by 50 per cent, preparations for the commissioning  of the new works are ramping up. 
        
        This involves a rigorous testing process,  which is currently underway to ensure the new structures are fully watertight  and all the new equipment operates correctly before we start to use it. 
        
This process is nearly complete on the new  inlet works and primary settlement tanks – where we will remove grit,  rags and the heaviest solids from the large volume of sewage that enters  the site. 
        
        Next in line are the recently completed aeration  lanes – where we pump air into the wastewater to encourage naturally occurring  micro organisms to break down the organic matter. 
        
        In order to conserve as much drinking water  as possible we are using treated water from the works, known as final effluent,  for the testing process.  This final effluent will be reused to test  each of the five aeration lanes, cutting water usage by around 80 per cent  – equivalent to the daily water use of around 1 million people. 
        
        Elsewhere, work to reduce the height of the  western embankment is entering its fourth month, with soil being removed  at a steady pace as we continue to fill around the recently completed tanks.  We are also using final effluent here, to damp down the soil on the western  embankment where necessary to minimise dust. 
        
        Thank you for bearing with us while carry  out work to improve Mogden, which will reduce the amount of sewage that  overflows into the River Thames after heavy rain. 
        
        Come and meet the team 
        
        On Thursday 31 May, from 5pm to 6.30 pm,  we will be holding an informal drop-in session where you will be able to  discuss the improvement work at Mogden with members of the project team. 
        
        This will be held at Twickenham Stadium.  On arrival please report to reception at Rugby House Door A, situated in  the South Stand. Free car parking is available in the main car park and  refreshments will be provided. 
        
        We will continue to update you on our progress,  but if you have any questions please call 0845 641 0030 and quote ‘Mogden’.   Our lines are open 24 hour a day. 
            
         
                  